Balance · 3
Contract tiers can only be raised after 3 days of performance data, and raising more than one tier requires 5 days.
contract tier raise requirementIf performance averages below 50% for three consecutive days, the contract tier is lowered by two and the penalty is withdrawn.
contract auto-downgrade ruleDowngrading a contract assesses a $250 penalty per tier downgrade, plus an extra penalty that shrinks the longer the contract has been running.
contract downgrade penalty
Economy · 1
Payments for captive service are now received before shop crew wages are paid.
captive service payment timing
Controls · 1
The Lean Left/Right bindings are now used for overhead camera rotation, and their orientation was fixed.
overhead camera rotation binding
System · 2
Customer performance is now updated at midnight.
customer performance update timingConnelly and Walker no longer share storage between the camps, so existing saves start with 0 logs/pulpwood in those camps' storage.
shared camp storage
Fix · 4
MU logic now uses the correct locomotive as its target.
mu logic locomotive targetMap icons with incorrect scale were fixed.
map icon scaleReputation no longer fails to update due to unexpected data.
reputation updateA shop crew count error of -1 was fixed.
shop crew count